Project Information

Townsen Park-n-Ride Multimodal Connector Harris County - Precinct 4 1/8/2015 8:51:18 AM

Project Narrative

The US 59 to I-45 corridor is undergoing a tremendous surge in development due to the influx of employees associated with new development by energy companies such as Exxon-Mobil and Southwest. Construction of these huge company complexes is nearing completion. They are located right next to the Spring Creek Greenway Trail system and will be linked in the near future by the proposed Townsen Park-n-Ride Multi-Model Connection to the Metropolitan Transit Authority of Harris County, Texas (METRO) bus terminal at Townsen Park-N-Ride. It is important to establish linkage to an alternative transportation mode such as Park-n Ride bus terminals and existing anchor parks along existing greenway trail systems. Traffic Congestion occurs within the project area and with future growth, the congestion will increase, providing a need for other forms of transportation and connectivity within the area. The proposed Townsen Park-n-Ride Multi-Modal Connector will provide a critical link to public transportation, Ride-Share parking, the regional Spring Creek Greenway Trail project, the regional Cypress Creek Greenway Trail project, and over 100-miles of hike and bike trails located throughout the master planned community of Kingwood. Furthermore, residents living along the greenway in subdivisions from US 59 to I-45 will immediately benefit from the prospect of alternative transportation to the bus terminals at the Park-n-Ride as well as existing anchor parks along the developed greenway. The Townsen Park-n-Ride Multi-Modal Connector takes the existing trails to another level, creating a regional transportation hub and an alternative mode of transportation to METRO buses and downtown destinations for thousands of residents. Approximately 22,000 residents live within 5 miles of the Townsen facility as measured along the greenway trails. About 15,000 of these residents are 60-years of age or younger and would have the opportunity to utilize an alternate mode of transportation. Also, health conscience residents of the region would have access to enjoy the Spring Creek Greenway experience and visit the Historic 1931 Bevil Jarrel Memorial Bridge using the METRO transportation network. The project is a proposed multimodal connector hike/bike trail that connects the Townsen Park-n-Ride with the regional Spring Creek Greenway trail system in northeast Harris County, Texas. The limits of the project are from the Townsen Park-n-Ride to the historic US 59 Bevil Jarrel Memorial Bridge. The project is approximately 0.7 miles in length and will affect 0.77 acres of land. The project area is located adjacent to the US 59 southbound frontage road, approximately 0.4 miles south of the San Jacinto River and 0.2 miles north of Townsen Boulevard. The 12' wide concrete trail will be routed mostly within TxDOT right-of-way (ROW) and includes a clear-span pedestrian bridge over a drainage ditch and under an existing frontage road bridge, allowing pedestrians and cyclists to safely travel to their destination. A no-build alternative was analyzed but was shown to not alleviate the mobility issues that will occur in the area. It was deemed that a no-build alternative would cause an environmental impact to the area. An alternate route was also analyzed; however utilities and ROW obstacles showed the alternative to not be cost effective.

Project Narrative

No

Categorical Exclusion (CE) (c)(3) Construction of bicycle and pedestrian lanes, paths, and facilities No 06/02/2014 Yes 1 07/01/2015 Yes Harris County Public Infrastructure Department (HCPID), through its engineering consultant, will be responsible for the utility coordination throughout the project with the assistance of TxDOT. HCPID will also be financially responsible for the cost of utility relocation. Minimal utilities are anticipated to be impacted in the project area. Preliminary on-the-ground surveys have been conducted for the 30% plans. Yes The project will improve the traffic flow and use of the Townsen Park-n-Ride for METRO. METRO is involved with and actively supports the project. METRO has plans to improve the Townsen Park-n-Ride due to the multimodal connector that is being proposed.

Support Letters.pdf

Local landowners were identified and informed of the project intention. The process involving the acquisition of ROW from a property owner has already commenced. The property owner stated that he is supportive of the project and will comply with the need to acquire some of his property. Meetings with the City of Humble and METRO have also occurred and all involved with the project are supportive and receptive.

Public Outreach.pdf

The 30% design is complete along with several environmental documents to speed up environmental clearance for the project. Cultural Resources, Natural Resources, and Environmental Constraints have already been completed for the project.

Attachment 1_6_15_smallest_opt.pdf

Map/Location

TIP Application attachment.mpk

Project Budget

Project Budget010715.xlsx

No

No

Screening Questions

Yes AASHTO design guidelines for pedestrian and/or bicycle facillites were used for the design.

Evalutation Questions - Pedestrian/Bicycle Projects

Design Standards

Connectivity

Barrier Elimination

Pilot Projects

Safety

Does proposed facility:

Existing Plans/Studies

Funding Leverage

Underserved Population Access

Is all or part of the proposed facility located within a Census Tract that has a higher proportion of the following populations than the regional average:
H-GAC to conduct analysis based on the GIS/map project location provided above