Project Information

CR 101 Widening from CR 90 to FM 1128 Brazoria County 1/12/2015 3:28:18 PM

Project Narrative

The north end of Brazoria County has experienced tremendous growth over the last two decades. CR 101 was originally constructed as a roadway used for agricultural purposes. Currently, there is a lack of east/west thoroughfares in northern Brazoria County. Congestion occurs along existing east/west thoroughfares in the area. CR 101 is a narrow two-lane asphalt road with roadside ditches and no shoulders. The roadside ditches are steep in many areas along the corridor. The City of Pearland is widening Bailey Road which connects to CR 101 on the east side of this project. The improvements to Bailey Road will result in CR 101 acting as a bottle neck between SH 35 and SH 288. This project will provide the northern Brazoria County region with another east west corridor from SH 35 to SH 288 and reduce congestion in the region. The completion of this project will fill a gap between SH 35 and SH 288 and relieve regional traffic along FM 518. Converting the two-lane facility to a four-lane divided roadway with raised median, and the addition of storm sewers along the corridor that will reduce the steep roadside ditches to shallow swales, will provide a safer roadway. The existing 2-lane facility will be widened from CR 90 to FM 1128, approximately 2 miles. The proposed roadway will be a concrete road with curb and gutter consisting of four 12-foot wide lanes and an 18-foot wide raised median. Sidewalks will be constructed for pedestrian access. Concrete storm sewers will be also be installed. An 8-acre storm water detention pond will be constructed to mitigate storm water runoff. A traffic signal will also be installed at the intersection of CR 101 and CR 89. Alternative locations for the detention site were evaluated. Although this project has been designed as a single project, construction could be phased into 2 segments. CR 89 is a logical break for the segments. Also, construction of the signal can be done separately.

Project Narrative

No

Environmental Assessment (EA) Please Select Yes A Phase I Environmental Site Assessment in conformance with the scope and limitations of ASTM Practice E1527-2013 if the approximate 2 miles CR 101 and the proposed new right-of-way taking has been performed. This assessment has revealed no evidence of recognized environmental conditions in connection with the property. The review of the Wetland Report indicates that approximately 35 linear feet of roadside ditches within the project limits may be potentially considered as jurisdictional and therefore would require coordination with the US Army Corp of Engineer’s. Also, an area in West Mary's Creek where the outfall to the detention pond may be jurisdictional. A Preliminary Jurisdictional Determination will need to be conducted for the proposed project to ascertain the extent of jurisdictional wetlands. We anticipate minimal if any disruption of wetlands or Waters of the US and therefore and Nationwide Permit with No Notice should apply to the project. A determination should be available within 90-180 days of submittal to the USACE. 30/08/2015 Yes 20 30/12/2015 Yes Brazoria County will coordinate utility adjustments with the TxDOT District and Area offices. Procedures will follow TxDOT guidelines. Public utility owners (companies) legally share County right of way, so when major changes are made to roadways, they very likely affect utilities. Brazoria County will formally notify all affected utility owners of proposed work as early as possible and to coordinate utility adjustments with the utility owners. Typically, utility owners are responsible for moving their own facilities, including budgeting, locating existing lines, preparing plans, specifications and estimates, and letting contracts. Under some circumstances, Brazoria County may fund utility adjustments. Furthermore, utility adjustment plans may be made part of the project construction plans. When design of proposed underground features is approximately 60% complete, Brazoria County will send project construction plans to all utility owners so they may begin designing required adjustments. Continuous coordination and involvement of the utility owners throughout project development is essential to maintain the project schedule. For utilities outside of the existing right-of-way utility easements are identified during the right-of-way acquisition process. These easement interests are addressed during the right-of-way acquisition. No

Brazoria County held a public workshop to review this project with the public and all members of Commissioners' Court on November 12, 2014. At the meeting the project was presented with opportunity for comments and questions from the Court and the public. Commissioners' Court has approved the submission of this project by the attached Court Order. The City of Pearland has also shown support of the project in the attached Resolution.

2015 TIP Call - Court Order & Resolution.pdf

Construction plans have been prepared and are approximately 90% complete and substantially conform to requirements of state and federally funded projects. Brazoria County is prepared to make revisions to the plans should it be found that such changes are necessary for federal funding. Brazoria County is actively acquiring right-of-way for the project. A total of 44 parcels have been acquired. Brazoria County is actively pursuing the acquisition of the remaining 20 parcels which should be acquired by the end of 2015. Construction plans and the preliminary engineering report exceed the 30MB limit of this application but can be provided if requested.

Map/Location

CR 101.jpg

Project Budget

CR 101 - Project Budget.xlsx

No

No

Evalutation Questions - Major Investments

Benefit/Cost Methodology

Please attach the completed BCA Excel worksheet and narrative explanation of analyses used

CR 101 - Generic Benefit Discounting.xlsx

Safety Benefits Criteria.docx

Narrative Benefits

The existing conditions provide 2 narrow asphalt lanes, little or no shoulders and fairly deep ditches along both sides of the road way with inadequate drainage. This combination doesn’t meet current safety standards and will be improved with the proposed project to a 4-lane divided concrete boulevard section. Safety is further enhanced by inclusion of raised medians and dedicated left turn lanes and median openings located for major traffic generators along the roadway. Currently, no sidewalks are provided within the limits of the project allowing for an unsafe mix of pedestrians and vehicles. Sidewalks will be provided along the roadway and will tie to existing sidewalks at the termini of the project. This creates a continuous dedicated area for pedestrians, removing conflicts with vehicular traffic. Steep roadside ditches are removed with the proposed project and replaced with a storm water conveyance system utilizing curb and gutters. Small adjacent swales may be added beyond the sidewalk to collect minimal amounts of outside storm water current flowing to the roadway.

CR 101 - Safety Benefits.xls

On the east side of this project, Pearland has funded the construction widening of Bailey Road to a 4 lane roadway from FM 1128 to Veterans. On the west side, CR 101 already exists as a 4 lane roadway from SH 288 to CR 90. This project will connect these two 4 lane sections from CR 90 to FM 1128 providing additional needed capacity from the east side of Pearland to SH 288, essentially connecting SH 288 to SH 35. This connection will not only relieve congestion on CR 101 but will also take the overwhelming pressure and congestion off of FM 518 which runs east and west through Pearland.

CR 101 is currently a two lane asphalt road that was constructed decades ago for the simple purpose to provide access to agricultural traffic through a rural area. In the last two decades, this area has seen tremendous growth and the traffic using this roadway is greater in volume and scale for its current design. Therefore, Brazoria County is investing tremendous money in keep the road in safe traveling condition. The proposed roadway will be a concrete roadway that is designed for its current use; a suburban higher density area that has both residential and commercial use. This proposed section will lessen Brazoria County's on-going maintenance and provide greater asset management capabilities.

The area served by CR 101 is ready for development and redevelopment of tracks in use. However, due to the constraints of the roadway, this new economic development is hindered. Therefore, providing a roadway that is designed to handle the traffic in the area would allow the land served by the roadway to develop to its highest and best use. This development will provide economic benefit to the property owners, residents of Brazoria County, City of Pearland and the City of Manvel.

The project will avoid impact to natural and cultural resources.