Installation of Intelligent Transportation Systems on US 59 from Reading Rd to Spur 10 in Ft. Bend Co. Texas Department of Transportation 1/12/2015 8:30:08 AM

Project Narrative

This project will provide necessary expanded coverage of existing incident management, congestion management, and traveler information systems infrastructure for the TxDOT Houston District (TranStar) region. This improvement project will allow TranStar to move closer to achieving the goal of DISTRICT-WIDE integrated coverage. A portion of this project is a current hurricane evacuation route from SH 36 to Spur 10. This project will improve real-time incident detection, responsiveness and notification; and also improve real-time traffic monitoring and reporting capabilities of recurring congestion. A portion of this project is a current hurricane evacuation route from SH 36 to Spur 10. The project will involve instrumentation of a freeway, US 59 (Southwest Freeway), from Reading Road to Spur 10 in Ft. Bend County. Specifically, this project will include the installation of 10 miles of 144-strand fiber trunkline (10 miles of conduit currently exists in this project segment; including 15 closed-circuit cameras, 5 dynamic message signs, 6 radar-based vehicle sensing devices, and 5 travel time readers. This project will provide monitoring of a segment of a key hurricane evacuation route. It will provide the future capability to deploy ITS along SH 36 and Spur 10 for providing evacuation monitoring along with deploying traveler information capabilities. None. However, since this is an ITS infrastructure expansion versus conventional roadway capacity expansion, the inherent benefit is to gain more capacity utilization of the existing facility without any environmental impacts or requiring additional right-of-way/heavy construction.

Project Narrative

Yes

TIPS Project 300714.pdf

Categorical Exclusion (CE) (c)(21) Deployment of electronics, photonics, communications, or information processing No 01/04/2016 No Yes No Utility Adjustments will be needed. No

No Public Involvement activities are needed.

The conduit is being installed by a road construction project. The design plans can be at 30% within 30 days of notice to start design.

TIP Project Scope 300714.xlsx

Map/Location

TIPS Project 300714.pdf

Project Budget

Project Budget TIP Application 300714.xlsx

Yes

OM Budget for TIP Application 300714.xlsx

No

Screening Questions

Yes ITS technology deployment is typically at least 7-10 years before retrofit or total replacement is required.

Evalutation Questions - ITS Projects

Benefit /Cost Methodology

H-GAC to conduct analysis based on the GIS/map project location and project scope information provided above.

Congestion Safety

Incident/Event Management

Coordination

System Migration/Expandability

Asset Mgmt/Efficient Operations

Continuity Operations

System Lifecycle/Maintenance Issues