Who is Completing the Application?

Please provide contact information for the person who will complete the online application for this project. The email address and password entered here will be used to complete and submit both Pre-Applications and Applications.

Karen McKinnon

Assistant County Engineer

979-864-1265

[email protected]

Primary Agency Information

Please provide contact information for the agency official who is representing the project sponsor. This individual will be considered the official applicant and must be authorized by their agency to submit this request for funding and make necessary assertations and representations on the agency’s behalf.

Brazoria County

L.M. 'Matt' Sebesta

County Judge

979-864-1200

[email protected]

111 East Locust Street, Suite 102A

Angleton

TX

77515

Additional Agency Information

City of Angleton

Scott Albert

City Manager

979-849-4364

[email protected]

121 S. Velasco Street

Angleton

TX

77515

Project Information

CR 44 Widening From SH 288 to Loop 274

Brazoria County

CR 44

From SH 288 to Loop 274

Brazoria County has experienced tremendous growth in the past two decades and it is anticipated to continue to have extreme growth over the next few decades. It is forecasted that Brazoria County will increase in population by 50% by 2040. Brazoria County must respond to this intense growth by developing our planned thoroughfares throughout the county to meet current and future needs. CR 44 from State Highway 288 to Loop 274 is a planned thoroughfare for both the City of Angleton and Brazoria County. It serves as an entrance into downtown Angleton and leads directly to the Brazoria County Courthouse Complex. In August 2018, Angleton Christian School opened along CR 44 near SH 288. This school provides education for grades Pre-Kindergarten through 12th and has increased traffic along the roadway. We predict this school’s enrollment and traffic demand will continue to grow over the next 5 years. Across CR 44 from the school, a new subdivision, containing approximately 600 homes, is currently in the planning phase which will also increase traffic along this section of roadway. The south end of the proposed project is comprised of the existing residential developments Angleton Meadows Subdivision and Heritage Oaks along opposite sides of the roadway. In addition to increased traffic volumes, this corridor also needs to upgrade roadway conditions. The current roadway has little to no shoulders, no sidewalks, and narrow lane widths which do not meet current safety or design standards. Costly maintenance repairs will be required along this section of roadway as traffic increases beyond the intended purpose of the current asphalt roadway. This project is needed to manage the increase in traffic volumes, improve safety for drivers and pedestrians, improve drainage, and prevent costly maintenance repairs.

The proposed improvement of CR 44 begins at the existing eastern jug handle of State Highway 288 and extends to Loop 274 for a distance of approximately 7,500 linear feet (1.42 miles). The right-of way width will be increased from the existing 90-foot to the proposed 120-foot right-of-way. The project will remove the existing two lane asphalt pavement roadway and construct a four lane divided concrete pavement boulevard with raised medians, curb and gutters, and sidewalks. A storm sewer system will replace the existing open ditches and will outfall to a proposed detention pond. Sidewalks will be constructed along the roadway to accommodate the pedestrian traffic from the subdivisions to the school and to the businesses along the corridor. A new traffic signal will be installed at the intersection of CR 44 eastern jug handle of SH 288 to manage the increased turning movements and new roadway geometry. Also, the existing traffic signal at the intersection of CR 44 and Loop 274 will be updated to accommodate the new roadway geometry and sidewalks.

The purpose of this project is to alleviate traffic congestion resulting from recent and future population increases and improve roadway conditions to current design and safety standards. Adding capacity to this corridor by constructing this proposed four lane divided section of roadway will increase mobility and enhance safety. This route provides direct connectivity to the Angleton Central Business District, which includes over 2000 jobs and the seat of Brazoria County government. It is essential for Brazoria County to continue to expand and build thoroughfares to increase mobility and create safe conditions for drivers and pedestrians throughout the county.

No

No

Less than $100 million

(Expand) Roadway Added Capacity/New Construction/Complete Streets

11060000

CR 44 Letters.pdf

Project Development/Readiness

Not Started

Environmental Assessment (EA)

11/01/2021

No

No

No

Yes

Yes

05/02/2022

05/02/2022

11/06/2023

33

4

No

No

CR 44 Timeline.pdf

Map/Location

CR 44 EXHIBIT.pdf

Project Budget

CR 44 Widening Project Budget.pdf

No

Benefit/Cost Analysis

Roadway-Safety-Benefits_CR 44.xlsx

1030201865844PM.xlsx

Roadway-Emissions-Benefits_CR 44.xlsx

CR 44 BCA Narrative.pdf

Planning Factors - Connectivity to Employment/Eliminates At-Grade Railroad Crossings

Yes

901 - 1000

No

Planning Factors - Environmental Justice

No

Planning Factors - Improves Corridor Level of Travel Time Reliability (LOTTR)

0.01 – 0.10

lottr-estimation_CR 44.xlsx

Planning Factors - Improves Multimodal LOS

No

No

Yes

Brazoria County is proposing a 10' sidewalk along the widen roadway to allow for pedestrians and bikes to safety travel along the corridor.

Planning Factors - Planning Coordination

Yes

Brazoria County Thoroughfare Plan; City of Angleton Thoroughfare Plan

https://tinyurl.com/BrazoriaEngineering ; https://brazoriacounty.sharefile.com/d-s29f31450039494c8

Planning Factors - Roadway Hierarchy/Freight System Priority/Evacuation Route

Minor Arterial

No

No

No

Yes